The Challenge
The refinery relied on periodic manual inspections of SF6 gas conditions, which failed to detect localized insulation defects or early-stage PD activity:
-
Absence of Continuous PD Visibility
No real-time visibility into internal discharge activity occurring inside sealed GIS compartments
-
Delayed Detection of SF₆ Insulation Degradation
The lack of correlation increased the risk of undetected insulation weakening and sudden dielectric failure.
IMPACT OF GIS FAILURES:
- High repair and replacement costs
- Long outage durations often last weeks or months